Phased implementation
According to floors, room groups or defined construction phases.

We transform existing hotels into contemporary, economical and inspiring spaces - with well thought-out planning, precise implementation and minimal disruption to ongoing operations.
Discuss your projectOUR SERVICES
Whether individual rooms, public areas or a comprehensive modernization – we develop tailor-made solutions tailored to your property, your business and your investment goals.

HOTEL RENOVATION DURING OPERATION
Through well-thought-out stage planning and clear logistics, renovation measures can be carried out on suitable projects while other hotel areas continue to be used.
According to floors, room groups or defined construction phases.
Separate material and guest routes, coordinated deliveries and disposal.
Coordination of noise-intensive work and dust-intensive activities.
Adjustment to occupancy, season and agreed handover dates.
OUR PROCESS
A structured process for transparency, efficiency and first-class results - with clear time frames and defined responsibilities.
1 week
Record room conditions, usage requirements and technical framework conditions.
2 weeks
Define equipment, materials, scope of services and cost framework.
2 weeks
Release products, coordinate delivery times and ensure material availability.
9-10 weeks
Coordinate delivery dates, coordinate material transport and prepare delivery.
2-4 weeks
Remove existing equipment, prepare surfaces and install new equipment.
Under 16–20 weeks
An FF&E renovation can usually be implemented more quickly than a complete renovation.